General Contractor: Gilbane/Clark Joint Venture

Contract Amount: $ 4,750,000

The scope work for this project includes:
  • Demolition of asphalt parking, concrete curbs, islands, and trees
  • Underground utility removals
  • Installation of a beam and wood lagging earth retention system up to 50 feet deep
  • Mass excavation of over 125,000 cubic yards
  • Excavate and backfill for building foundations, mechanical and electrical